Verifying proper operation
After replacing a messaging system component, check the following to verify that the component
is operating properly:
If applicable, verify that the green LED is lit continuously or blinking. If not, try reseating the
component.
From the System Manager, navigate to the Hardware Status and System Summary tabs to
confirm the component failure alert no longer appears. The status should be (Good).
Wait times for hard disks
If the hard drive is part of a volume, the following wait times apply:
Removal
Less than 3 seconds for the LED to turn off
Insert
Less than 1 second for first disk activity
Less than 15 seconds for the disk to be ready for REBUILD. The LED blinks at 1 Hz.
NOTE: The transition to solid green depends on how long the REBUILD takes (the LEDs
indicate REBUILD).
If the hard drive is not part of a volume, the following wait times apply:
Removal
No indication appears because the LED is already off
Insert
Less than 1 second for the first disk activity to appear
Less than 15 seconds for the disk to be ready to use
Removing and replacing the server interposer board
This section describes how to remove and replace the server interposer board in the messaging
system.
Removing the server interposer board
To remove the server interposer board:
1. Use System Manager to identify the failed component.
2. Verify the failed component by checking for a blinking amber LED on the failed component
(see Table 4 (page 53)).
3. Power off the system:
1. Shut down blade 2 by clicking on Start and then Shut Down while you are connected to
blade 1.
2. Shut down blade 1 by clicking on Start and then Shut Down while you are connected to
blade 2.
3. Power off the expansion nodes, if present, by pressing and holding the power button at
the back.
4. Power off the storage solution by pressing and holding the power button at the back of
the enclosure.
5. Disconnect the power cables.
4. Extend the hard drive drawer:
74 Removing and replacing hardware components