Specifications
General Site Preparation Guidelines
Sample Site Inspection Checklist
Chapter 2
40
26. Are there any equipment servicing hazards
(loose ground wires, poor lighting, and so on)?
Cooling
No. Area or condition Yes No
27. Can cooling be maintained between 20°C and 55°C (up to
5,000 ft.)? Derate 1°C/1,000 ft. above 5,000 ft. and up to
10,000 ft.
28. Can temperature changes be held to 10°C per hour with
tape media? Can temperature changes be held to 20°C per
hour without tape media?
29. Can humidity level be maintained at 40% to 60% at 35°C
noncondensing?
30. Are air conditioning filters installed and clean?
Storage
No. Area or condition Yes No
31. Are cabinets available for tape and disc media?
32. Is shelving available for documentation?
Training
No. Area or Condition
33. Are personnel enrolled in the System Administrator’s
Course?
34. Is on-site training required?
Table 2-5 Site Inspection Checklist (Continued)
Please check either Yes or No. If No, include comment# or date Comment or Date