Specifications

General Site Preparation Guidelines
Sample of an Installation Schedule
Chapter 2
37
Sample of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
60 days before installation
Floor plan design completed and mailed to HP (if required to be an HP task)
30 days before installation
Primary power and air conditioning installation completed
Telephone and data cables installed
Fire protection equipment installed
Major facility changes completed
Special delivery requirements defined
Site inspection survey completed
Delivery survey completed
A signed copy of the site inspection and delivery survey mailed to HP
Site inspection and predelivery coordination meeting arranged with an HP representative to review
the inspection checklist and arrange an installation schedule
7 days before installation
Final check made with an HP site preparation specialist to resolve any last minute problems
NOTE Not all installations follow a schedule like the one noted above. Sometimes, a HP 9000 rp3410
or HP 9000 rp3440 server is purchased through another vendor, which can preclude a rigid
schedule. Other conditions could also prevent following this schedule. For those situations,
consider a milestone schedule.
Site Preparation—Schedule with the customer as soon as possible after the order is placed.
Site Verification—Schedule with the customer a minimum of one to two days before the
HP 9000 rp3410 or HP 9000 rp3440 server is scheduled to be installed.