Instruction Manual

Document 2.4.96, Revision 0
March, 2013
14
Single-Phase Pad-Mounted Compartmental-Type Distribution Transformers
2. Checking for Leaks—Check the tank to make
sure there are no uid leaks.
3. Observing Operation—After the transformer is
initially energized, visually inspect it periodically,
to make sure that no abnormal conditions are
observed.
4. Checking Gauges—Observe the uid level and
uid temperature gauges, if provided, to conrm
the proper uid level and temperature.
5. Audible Sound
It is normal for transformers
to emit an audible humming sound, which is
primarily caused by alternating magnetic ux in
the transformer core. Amplitude and harmonic
content of the sound is inuenced by transformer
size, the energizing voltage level and sinusoidal
purity, load conditions and acoustic conditions
at the installation site. Refer to NEMA Standards
Publication TR-1 Transformers, Regulators and
Reactors, and IEEE Standard C57.12.90 IEEE
Standard Test Code for Liquid-Immersed Distri-
bution, Power, and Regulating Transformers, for
more information about design sound levels, and
factory sound testing. Unusual sounds should be
investigated, as this might indicate a potential
problem.
Locking the Terminal Compartment—Before leaving
the installation site, make sure the terminal compart-
ment is secure. Follow the procedures the “Single-
Door Terminal Compartment” or “Double-Door Termi-
nal Compartment” section, as applicable.