Service Manual
Table Of Contents
- Important Safety Information
- I. Construction and Water/Refrigeration Circuit Diagram
- A. Construction
- B. Icemaking Unit
- C. Water/Refrigeration Circuit Diagram
- II. Sequence of Operation and Service Diagnosis
- A. Sequence of Operation Flow Chart
- 1. Icemaking and Drain Cycle
- 2. Shutdown
- B. Service Diagnosis
- 1. Ice Production Check
- 2. Diagnostic Procedure
- C. Control Board Check
- D. Bin Control Check
- E. Float Switch Check and Cleaning
- F. Diagnostic Tables
- III. Controls and Adjustments
- A. Control Board
- 1. Control Board Layout Shown:
- 2. LED Lights and Audible Alarm Safeties
- 3. Ice Purge Cycle Bypass
- B. Controls and Adjustments
- 1. Default Dip Switch Settings
- 2. Infrared Sensor Shutdown Delay (S1 dip switch 1, 2, 3)
- 3. Drain Frequency Control (S1 dip switch 4)
- 4. Continuous Dispensing Timer (S1 dip switch 5 & 6)
- 5. Bin Control Selector (S1 dip switch 7)
- 6a. Mechanical Shutdown Delay (S1 dip switch 8) Auxiliary Code E-0:
- 6b. Agitation and Ice Purge Timer (S1 dip switch 8) Auxiliary Code F-0 and Later:
- 7. Mechanical Shutdown Delay (S1 dip switch 9) Auxiliary Code F-0 and Later
- 8a. Factory Use (S1 Dip Switch 9 & 10) Auxiliary Code E-0
- 8b. Factory Use (S1 Dip Switch 10) Auxiliary Code F-0 and Later
- C. Power Switch and Control Switch
- IV. Refrigeration Circuit and Component Service Information
- A. Refrigeration Circuit Service Information
- B. Component Service Information
- V. Maintenance
- VI. Disposal
- VII. Technical Information
- A. Specification & Performance Data Sheets
- 1. F-330BAJ
- 2. F-330BAJ-C
- B. Wiring Diagram
42
7) Replace the top and side panels in their correct position.
8) Move the power switch to the "ON" position, then turn on the power supply.
9) Replace the front panel in its correct position.
IMPORTANT! Seal Bolt Removal and Installation Instructions: Seal bolts must be
replaced once removed because seal material is one-time use only. If new seal bolts do
not have preapplied threadlocker, apply Loctite 243 or equivalent threadlocker to seal bolt
threads.
• Torque for F-330BAJ(-C): 11.1 ft-lb/15 N·m. Tighten 2 times. Allow at least 5 sec. in
between each tightening.
3. Removal and Replacement of Extruding Head
1) Drain the water from the evaporator.
a) Remove the front panel, then move the power switch to the "OFF" position.
b) Move the control switch to the "DRAIN" position.
c) Move the power switch to the "ON" position and allow the water to drain from the
evaporator.
d) Move the power switch to the "OFF" position, then turn off the power supply.
2) Remove the top and side panels.
3) Remove the strap connecting the spout to the chute assembly, then remove the spout.
4) Remove the cutter bolt (if applicable) or cutter and lift off the cutter and washer (if
applicable).
5) Remove the seal bolts from the extruding head and lift off the extruding head.
6) Place the new extruding head in place and tighten down with new seal bolts.
See "Seal Bolt Removal and Installation Instructions" above.
7) Replace the washer (if applicable), cutter, cutter bolt (if applicable), and spout.
8) Replace the top and side panels in their correct positions.
9) Move the control switch to the "ICE" position.
10) Move the power switch to the "ON" position, then turn on the power supply.
11) Replace the front panel in its correct position.