Service Manual
Table Of Contents
- Important Safety Information
- I. Construction and Water/Refrigeration Circuit Diagram
- A. Construction
- B. Icemaking Unit
- C. Water/Refrigeration Circuit Diagram
- II. Sequence of Operation and Service Diagnosis
- A. Sequence of Operation Flow Chart
- 1. Icemaking and Drain Cycle
- 2. Shutdown
- B. Service Diagnosis
- 1. Ice Production Check
- 2. Diagnostic Procedure
- C. Control Board Check
- D. Bin Control Check
- E. Float Switch Check and Cleaning
- F. Diagnostic Tables
- III. Controls and Adjustments
- A. Control Board
- 1. Control Board Layout Shown:
- 2. LED Lights and Audible Alarm Safeties
- 3. Ice Purge Cycle Bypass
- B. Controls and Adjustments
- 1. Default Dip Switch Settings
- 2. Infrared Sensor Shutdown Delay (S1 dip switch 1, 2, 3)
- 3. Drain Frequency Control (S1 dip switch 4)
- 4. Continuous Dispensing Timer (S1 dip switch 5 & 6)
- 5. Bin Control Selector (S1 dip switch 7)
- 6a. Mechanical Shutdown Delay (S1 dip switch 8) Auxiliary Code E-0:
- 6b. Agitation and Ice Purge Timer (S1 dip switch 8) Auxiliary Code F-0 and Later:
- 7. Mechanical Shutdown Delay (S1 dip switch 9) Auxiliary Code F-0 and Later
- 8a. Factory Use (S1 Dip Switch 9 & 10) Auxiliary Code E-0
- 8b. Factory Use (S1 Dip Switch 10) Auxiliary Code F-0 and Later
- C. Power Switch and Control Switch
- IV. Refrigeration Circuit and Component Service Information
- A. Refrigeration Circuit Service Information
- B. Component Service Information
- V. Maintenance
- VI. Disposal
- VII. Technical Information
- A. Specification & Performance Data Sheets
- 1. F-330BAJ
- 2. F-330BAJ-C
- B. Wiring Diagram
18
C. Control Board Check
Before replacing a control board that does not show a visible defect and that you suspect
is bad, always conduct the following check procedure. This procedure will help you verify
your diagnosis.
1) Check CB S1 dip switch settings to assure that they are in the factory default position.
For factory default settings, see "III.B.1. Default Dip Switch Settings."
Note: S1 dip switch 7determines bin control application:
BC: S1 dip switch 7 in the "OFF" position.
2) Move the power switch to the "ON" position and move the control switch to the "ICE"
position. The "POWER OK" LED turns on. Diagnosis "POWER OK" LED: Check that
the CB "POWER OK" LED is on. If not, check for proper supply voltage (115VAC) input
to the control transformer (power switch, power supply cord, breaker, and fuse). Next,
check for proper low-voltage (24VAC) output from the control transformer and that the
3A fuse is good. Check for 24VAC at CB K8 #1 (W/R) to CB K8 #2 (LBU). If 24VAC is
present and the "POWER OK" LED is off, replace CB.
3) 5VDC Output Checks:
CB K9 Connector: Control Switch (CB K9 #1 and #2) (open contacts for icemaking,
closed contacts for drain), High-Pressure Switch (CB K9 #3 and #4), Compressor
Control Relay (K9 #5 and #6).
CB K8 Connector: Bin Control (K8 #3 and #4) and Float Switch (K8 #5 (common),
#6(lower), and #7 (upper)).
When checking 5VDC control voltage, always place the red positive test lead from
the multimeter to the CB white K5 pin closest to the CB red K4 connector. See Fig. 1.
Then place the black negative test lead from the multimeter to the corresponding pin to
complete the 5VDC check.
Red positive test lead
to K5 pin closest to K4
connector
Fig. 1
Control Board K9 Connector
Red Positive
Test Lead
Black Negative
Test Lead
Multimeter
5VDC
Control Switch
white/black (W/BK)
High-Pressure Switch
yellow (Y) wires
Compressor Control Relay/
Gear Motor Protect Relay
(terminals #3 and #5)
white/orange (W/O)