Service Manual
Table Of Contents
- Important Safety Information
- I. Construction and Water/Refrigeration Circuit Diagram
- A. Construction
- B. Icemaking Unit
- C. Water/Refrigeration Circuit Diagram
- II. Sequence of Operation and Service Diagnosis
- A. Sequence of Operation Flow Chart
- 1. Icemaking and Drain Cycle
- 2. Shutdown
- B. Service Diagnosis
- 1. Ice Production Check
- 2. Diagnostic Procedure
- C. Control Board Check
- D. Bin Control Check
- E. Float Switch Check and Cleaning
- F. Diagnostic Tables
- III. Controls and Adjustments
- A. Control Board
- 1. Control Board Layout Shown:
- 2. LED Lights and Audible Alarm Safeties
- 3. Ice Purge Cycle Bypass
- B. Controls and Adjustments
- 1. Default Dip Switch Settings
- 2. Infrared Sensor Shutdown Delay (S1 dip switch 1, 2, 3)
- 3. Drain Frequency Control (S1 dip switch 4)
- 4. Continuous Dispensing Timer (S1 dip switch 5 & 6)
- 5. Bin Control Selector (S1 dip switch 7)
- 6a. Mechanical Shutdown Delay (S1 dip switch 8) Auxiliary Code E-0:
- 6b. Agitation and Ice Purge Timer (S1 dip switch 8) Auxiliary Code F-0 and Later:
- 7. Mechanical Shutdown Delay (S1 dip switch 9) Auxiliary Code F-0 and Later
- 8a. Factory Use (S1 Dip Switch 9 & 10) Auxiliary Code E-0
- 8b. Factory Use (S1 Dip Switch 10) Auxiliary Code F-0 and Later
- C. Power Switch and Control Switch
- IV. Refrigeration Circuit and Component Service Information
- A. Refrigeration Circuit Service Information
- B. Component Service Information
- V. Maintenance
- VI. Disposal
- VII. Technical Information
- A. Specification & Performance Data Sheets
- 1. F-330BAJ
- 2. F-330BAJ-C
- B. Wiring Diagram
10
II. Sequence of Operation and Service Diagnosis
A. Sequence of Operation Flow Chart
1. Icemaking and Drain Cycle
F-330BAJ(-C) Sequence Flow Chart
1-in-1 drain cycle. DV opens for 2 sec. every hour
(CB S1 Dip Switch 4).
Icemaker status does not change.
LFS closed
UFS closed
FZT starts
FT terminated
WV de-energized
3. 1-in-12 Drain Cycle
& Restart (optional)
UFS open
LFS open (WV on)
FT starts (90 sec.)
FZT terminated
WV energized
Comp continues
GM continues
FM continues
1. Startup
2. Ice Purge Cycle
WV energized
Comp energized
GM continues
FM continues
2. 1-in-1 Drain Cycle
Comp de-energized
GM continues
FM continues
1. Fill Cycle
3. Freeze Cycle
LFS closed
UFS closed
FZT starts (30 min.)
FT terminated
WV de-energized
Comp continues
GM continues
FM continues
Low Water Safety
Purge Timer
UFS open
WV energized
Comp de-energized
GM continues
FM continues
DV energized
GM de-energized
FM de-energized
10-min. DT terminated
DV de-energized
1-in-12 DT reset
5 min.
4. Icemaker Restart
2. Ice Purge Cycle
3. 10-Min. Drain
If Fill > 90 sec. FT
1-beep alarm sounds
WV continues
When UFS closes
alarm resets and
2. Ice Purge Cycle starts.
FT Maximum
90 sec.
4. 1-in-12 Drain Cycle - Although the factory default 1-in-1 drain cycle
is recommended, a 1-in-12 drain cycle is available. For 1-in-12 drain
cycle sequence, see "3. 1-in-12 Hour Drain Cycle & Restart (optional)."
Re๎ll
FT Maximum
90 sec.
90 sec. FT exceeded,
90 sec. PT starts and
1-beep alarm sounds
90. sec. PT terminates
unit shuts down and
1-beep alarm continues.
When UFS closes, alarm
resets and 2. Ice Purge
Cycle starts.
WV continues
GM de-energized
FM de-energized
1. DT Initiates DC
To bypass, press the
"SERVICE" button after
GM starts.
5 min.
to "1. Fill Cycle" above
90 sec.
(CB S1 dip switch 4 "ON")
FT off (90 sec.)
5 or 30 sec.
(S1 Dip Switch 7)
EH energized
GM energized
FM energized
1. DT Initiates DC
Continued uninterrupted
operation
DV energizes for 2 sec.
2. Continued Operation
DV de-energizes, no
interruption in ice production
30-min. FZT
Startup
FZT exceeded (LFS does not
open): CB shuts down icemaker
and sounds a 5-beep alarm.
Legend:
BC-bin control
CB-control board
Comp-compressor
DC-drain cycle
DT-drain timer
DV-drain valve
EH-evaporator heater
FM-fan motor
FT-๎ll timer (low water safety)
FZT-freeze timer
GM-gear motor
LFS-lower ๎oat switch
PT-purge timer
UFS-upper ๎oat switch
WV-inlet water valve
Low Water Safety
Shutdown
(CB S1 dip switch 4 "OFF")
Normal Operation
Power Switch "ON"
Control Switch in "ICE"
POWER OK LED on
BC Closed