Installing the Charge Rack
DIAD 6 Charge Rack Manual
Installing the Charge Rack
Inspection of the DIAD 6 Charge Rack
The DIAD 6 Charge Rack will be shipped by Honeywell Scanning and Mobility, approximately
eight weeks prior to the center’s first day use of DIAD 6s. Upon arrival the shipment needs to be
inspected by Site/District coordinator for any shortages or damages.
Package Contents
Item (Quantity)
Part Number
DIAD 6 Charge Rack (1)
CN85-CR (wired)
CN85-WCR (wireless)
Power Cord, US, IEC 320-C13 (1)
77900506E (with ferrite PN 10008320 attached)
Side Guard Kit (1)
containing:
Right Guard Panel (1)
Left Guard Panel (1)
Screw 8-32x1/2” (4)
99EX-CR-NRGUARDKIT
Regulatory Sheet (1)
n/a
Reporting Shortages or Damages
Immediately report any problems with the shipment to the District TSG Manager. District TSG
should contact Julie Rutt via email (nat1jar@ups.com) with the following information:
RRDDSLIC of the location that is missing equipment or received damaged parts.
The serial number of the damaged/missing part(s).