14 Installation of Lonworks Board Honeywell
4. Installation of Honeywell NX LonWorks C4 Option Board
!
NOTE
MAKE SURE THAT THE FREQUENCY CONVERTER IS SWITCHED
OFF BEFORE AN OPTION OR FIELDBUS C4 OPTION BOARD IS
CHANGED OR ADDED!
A
Honeywell NX frequency converter
B
Remove the cable cover.
C
Open the cover of the control unit.
Continues on next page