User Guide
Table Of Contents
- 1. General
- 2. LonWorks C4 Option Board Technical Data
- 3. LonWorks Fieldbus C4 Option Board Layout and Connections
- 4. Installation of Honeywell NX LonWorks C4 Option Board
- 5. Commissioning
- 6. LonWorks Interface
- 7. Fault Tracking
- 8. Appendix 1
- 9. General Info
- 10. BACnet CJ Option Board Technical data
- 11. Bacnet Fieldbus CJ Option Board Layout and Connections
- 12. Grounding Cable Shield
- 13. Led Indications
- 14. Installation of Honeywell NX BACnet CJ Option Board
- 15. Commissioning
- 16. Fault Tracking
Honeywell LonWorks Layout and Connections 11
Figure 8.
3 Insert the data cables and the
shield in their respective
terminals. See Table 3.
Figure 9.
4 If the LonWorks C4 option
board was detached from the
control unit place it into slot E
of the control C4 option board
(see C4 option board
installation on page 14).
Otherwise attach the terminal
block. Fix the cable on the
frame with the clamp.
Figure 10.