Technical Specifications
4) Install gypsum wallboard to resilient channels as per manufacturer’s
installation instructions.
*If resilient channels are not installed, the gypsum wallboard must be
installed, staggering all seams, over the Homasote panels and screwed into
the ceiling joists as per gypsum wallboard manufacturer’s installation
instructions.
Resilient Channels Installed To
Ceiling Joists
1) Install resilient channels (or equal), spaced a maximum of 16" o.c., to
ceiling joists. Use sufficient length screws to penetrate into the ceiling
joists a minimum of 3/4"
2)
Screw Homasote panels using standard dr
ywall screws directly into
resilient channels. Allow for 3/16" expansion joint at all panel edges.
3) Screw Homasote panels 4" - 6" o.c. along panel edges and 10"-12" o.c.
at intermediate supports.
4) Gypsum wallboard is to be installed, staggering all seams, over the
Homasote panels and screwed into the resilient channels as per
gypsum wallboard manufacturer’s installation instructions.
Ceiling Construction
Provide framing or furring at maximum 16" o.c. regard-
less of 440 SoundBarrier® or N.C.F
.R. Homasote® panel
thickness. All panel edges must fall on framing members.
The 8’ side of the Homasote panel must be installed
parallel to floor joists.
Homasote Installed To Ceiling
Joists
1) Screw Homasote panels into ceiling joists using standard drywall
screws of sufficient length to penetrate a minimum of 3/4". Allow for
3/16" expansion joint at all Homasote edges. The 8’ side of the
Homasote panel must be installed parallel to floor joists.
2)
Screw Homasote panels 4" - 6" o.c. along panel edges and 10"-12" o.c.
at intermediate supports.
3) Install resilient channels (or equal) spaced 24" o.c. over Homasote
panels. Use sufficient length screws to penetrate through the panels
and into ceiling joists a minimum of 3/4".
W
-2-A) Fabric-Wrapped 440 SoundBarrier To
Wood or Metal Framing
1) Apply fabric to 440 SoundBarrier panels using adhesive recommended
by fabric manufacturer for application to wood fiberboard. The fabric
adhesive must be applied to the face of the panel in the proper amount
to prevent bleed-through. Wrap fabric and glue around edges and
continue for 2” on backside of board.
Homasote is not responsible for
the appearance or performance of job-site fabric-wrapped panels.
2) Lay panels flat for the necessary time to allow adhesive to fully set.
3) Apply a 3/8” bead of sub-floor adhesive meeting APA AFG-01
specification to intermediate studs in accordance with the adhesive
manufacturer’
s recommendation.
4)
Attach metal frame clips to long edges of 440 SoundBarrier panels
ever
y 12” o.c. See complete details in “2-D) Complete Instructions
For Metal Frame Clips.”
5) Apply fabric-wrapped 440 SoundBarrier panels to adhesive and fram-
ing, with recommended expansion gaps as stated at the bottom of page
1, applying hand pressure from the center of panel out to the ceiling
and floor where adhesive is located to insure positive contact. Screw
panels 6” o.c. to plates or blocking at floor and ceiling. Screws should
be sufficient length to penetrate 3/4” into framing. Hold screws 3/8”
back from edge of panels. Screw clips to framing and brace panels for
a minimum of 24 hours for adhesive to set.
W-2-B) Fabric-Wrapped 440 SoundBarrier To
Masonry Walls
1) As per APA recommendations, install wood furring strips to masonry
walls, not exceeding 16” o.c. for 1/2” 440 SoundBarrier panels and 24”
o.c. for 5/8” and 3/4” 440 SoundBarrier panels.
2)
Follow instructions “2-A) Fabric-Wrapped 440 SoundBarrier To Wood or
Metal Framing” for applying fabric wrapped 440 SoundBarrier panels.
W-2-C) Fabric-Wrapped 440 SoundBarrier To
Finished Walls
Apply wall panels following instructions in “2-A) Fabric-Wrapped
440 SoundBarrier To Wood or Metal Framing”. Apply adhesive to back of
440 SoundBarrier panels in 3/8” beads 16” o.c. and at perimeter, holding
adhesive back 3/4” from edge. 440 SoundBarrier panels must be aligned
such that edges fall on framing and must be fastened into wall framing.
W
-2-D) Complete Instructions For Metal
Frame Clips*
1) Lay out back of panel by drawing
lines at 16” inter
vals.
2)
Locate clips above the line on one
side and below on the opposite side.
(A staggered clip layout creates a
tongue-and-groove panel joint).
See diagram (right).
3) Seat the clips around the perimeter
of the board as shown in the
diagram. Do not damage panel edge.
(Use 7 clips per side for a
4’ x 8’ panels).
4) Apply a 3/8” bead of sub-floor adhe-
sive meeting APA AFG-01 specifica-
tion to intermediate studs in accor-
dance with the adhesive manufactur
-
er’s recommendation. A double bead
of adhesive is necessary on studs where adjoining panels fall.
5) Position panels (with clips installed) on any wood or metal framing.
T
ighten the joint with a floor leverage tool. Screw or nail panels to floor
and ceiling plates as per 440 SoundBarrier installation instructions.
Use low-profile screws to secure one series of clips to wall stud.
Stagger joints on opposite sides of the wall when possible.
6) The clips on the adjacent panel simply slide behind the fixed panel.
*Source: Cymax Systems, Inc.
6
440 SoundBarrier
®
and N.C.F.R.
®
Homasote
®
Combined Installation Instructions
C
CEILING APPLICATION