6. Open up the access covers over the load cells. All four corners of the platform and remove the tie
down bolts. It is recommended that the tie down bar be laid across the beams of the scale
weighbridge. We also recommend that the bolt be placed back into the threaded hole to avoid dirt
accumulation.
7. If scale system is installed on a concrete foundation anchors should be installed through the provided
anchor holes. One at each load cell access hole. Using a ¾” x 4” concrete anchor.
8. Make sure there is load on all load cells of the scale. No rocking from corner to corner. If there is