Install Instructions
Average Joint Cure Times for 
PVC, ABS and CPVC Solvent Cements
Pipe  
Diameter
 ½" ¾" 1"  1¼"  1½"  2" 3" 4" 6" 8"
Number 
of Joints
325 250 150 125 90 70 50 30 10 8
Contact Oatey Technical Services for cure times for pipe 
larger than 8" diameter.
This data is applicable only for new piping installations and not recommended for 
repair or cut-ins on hot and cold water distribution systems. Please contact Oatey 
Technical Service for recommendations on Cure Times for such applications.
DO NOT test PVC and CPVC piping systems with compressed air or gas.
NOTES: Cure schedule is the time required before pressure testing the system
- This chart can be used as a guideline to determine joint cure 
- Cure times stated are for conditions with relative humidity of 60% or less
+ In damp or humid weather, allow 50% additional cure time
Oatey Co.
Cleveland, OH 44135
800-321-9532
Oatey.com
PVC & ABS
Pipe Diameter
Temperature during assembly and cure period
60° to 
100°F
40° to 
60°F
20° to 
40°F
0° to 20°F
½" to 1¼"
Up to 180 psi 15 min 20 min 30 min
Please  
contact Oatey 
Technical 
Services for 
cure time 
information
180 psi + 4 hours 8 hours 36 hours
1½" to 3"
Up to 180 psi 30 min 45 min 60 min
180 psi + 8 hours 16 hours 3 days
4" to 5"
Up to 180 psi 2 hours 4 hours 36 hours
180 psi + 12 hours 24 hours 4 days
6" to 8"
Up to 180 psi 8 hours 16 hours 3 days
180 psi + 24 hours 48 hours 9 days
CPVC
Pipe Diameter
Temperature during assembly and cure period
60° to 
100°F
40° to 
60°F
20° to 
40°F
0° to 20°F
½" to 1¼"
Up to 180 psi 1 hour 2 hours
Please contact  
Oatey Technical  
Services for cure  
time information
180 psi + 6 hours 3 days
1½" to 3"
Up to 180 psi 5 hours 3 days
180 psi + 3 days 1 week
4" to 5"
Up to 180 psi 16 hours 1 week
180 psi + 1 week 3 weeks
6" to 8"
Up to 180 psi 1 week 2 weeks
180 psi + 2 weeks 4 weeks
Set Up & Curing Times
The set up/cure time is dependent on several 
factors. The pipe size, socket t, ambient 
temperature, relative humidity, solvent cement used 
and the system operating pressure should all be 
considered when determining set up/cure times. 
Average Handling/Set Up Times 
for PVC/CPVC Solvent Cements
Handling/Set Up Time is the time required prior to 
handling the joint. In damp or humid weather, allow 
50% additional time.
Average Number of Joints 
Per Quart of Solvent Cement
Pipe Diameter
Temperature during assembly
60° to 
100°F
40° to  
60°F
20° to  
40°F
0° to  
20°F
½" to 1¼" 2 minutes 5 minutes 8 minutes
10 minutes
1½" to 3" 5 minutes 10 minutes 12 minutes
15 minutes
4" to 5" 15 minutes 30 minutes 1 hour
2 hours
6" to 8" 30 minutes 90 minutes 3 hours
6 hours
Contact Oatey Technical Services for set up times for 
pipe larger than 8" diameter.
These gures should only be used as a general guide. Conditions in the eld 
may vary.
These gures are estimates based on laboratory testing. Conditions in the 
eld may vary.
©2019 Oatey SCS. All Rights Reserved. 
This information is based on data believed to be reliable but Oatey makes no warranties, express or implied, as to its accuracy and 
assumes no liability arising out of its use. The data listed falls within the normal range of product properties but should not be used 
to establish specication limits or used alone as the basis of design. Oatey’s liability to purchasers is expressly limited to the terms 
and conditions of sale. Oatey is a trademark of Oatey Co. All other trademarks can be found on Oatey.com. LCS358F WEB 03/20