Quick Start Manual
9
Installation, Operation & Maintenance  WDG AIR HANDLER SERIES  Heat Controller, LLC
3.  If the unit is suspended, it must be supported from the bottom 
near both ends as well as the middle to prevent sagging. 
The service access must remain unobstructed. If the unit is 
supported along the length of the front and back, the air handler 
only needs to be suspended at both ends. See Figure 1.
4.  If the unit is not suspended it must be supported as mentioned 
above and isolated carefully to prevent sound transmission. 
Vibration isolators (purchased locally) must be placed under the 
unit.
5.  It is always recommended that an auxiliary drain pan be 
installed under a horizontal air handler (See Condensate Drain 
Piping) to prevent possible damage to ceilings.
6.  Isolate the auxiliary drain pan from the unit or from the structure.
7.  Connect the auxiliary drain line to a separate drain line (no trap 
is needed in this line) and terminate according to national and 
local codes.
8.  If a return duct is connected to the air handler, it must be the 
same dimensions as the return opening shown in the outline 
drawing on Figure 2.
9.  Openings where fi eld wiring enters the cabinet must be 
completely sealed. Location of power entry is shown on the 
outline drawing.
10. After ductwork connections are made, seal airtight and per local 
codes.
Duct Connections
The supply and return air ducts should be connected to the unit 
with fl ame retardant duct connectors.
NOTE: No sheetmetal screws may be used to attach 
return ductwork on the side.
NOTE: Any duct board return connection can be made 
to the sides of the unit using tape or mastic.
Installation
Figure 1: Mounting Installation Options
Tranquility
E
ar
thPure
®
27
Rail
Auxiliary 
Drain Pan
Tranquility
EarthPure
®
27
Tranquility
EarthPure
®
27
Tranquility
EarthPure
®
27
Figure 2: Flange Attachment