Installation Guide
Set gable end wall on oor and secure top of wall
using one 2" screw into top plate (Fig A).
1
38
GABLE SOLID WALL
3" (7,6 cm)
2" (5,1 cm)
x18
2" (5,1 cm)
x2
x1
x14
1-1/2" (3,8 cm)
PARTS REQUIRED:
3" (7,6 cm)
x8
It is important to secure the gable end wall
in the following order:
ENSURE TOP OF WALL FRAMES ARE FLUSH.
3
2
Nail lower edge of panels to oor using 2" nails 6" apart.
Angle nail to hit oor frame (Fig. B).
ENSURE GABLE AND EAVE WALL PANELS
ARE FLUSH BEFORE SECURING.
You have nished standing your gable end wall.
FINISH
7
Secure gable end wall to oor using 3" nails (Fig. C).
Nail gable end wall panel to eave wall stud
using 1-1/2" nails 6" apart (Fig. C).
4
5
6
6"
(15,2 cm)
Flush
Fig. A
2" (5,1 cm)
Nails
Fig. B
2" (5,1 cm)
Nail
Angle nail to hit
oor frame.
Secure gable wall top frame 2 x 4 using one 3" screw
toe-screwed into eave wall frame at an angle as
shown (Fig. D).
6"
(15,2 cm)
3" (7,6 cm)
Nails
1-1/2"
(3,8 cm)
Nails
Fig. D
3" (7,6 cm)
Screw
BEGIN
Stand wall on oor.
2" (3,8 cm)
Screw
2"
(5,1 cm)
Screw
Fig. C
Move to the bottom of gable end wall and
secure bottom of wall using one 2" screw into
eave wall bottom plate (Fig A).
Flush
STEP 1 FIRST
SCREW
STEP 3
STEP 2 SECOND
SCREW
2"
(5,1 cm)
Screw
Flush
IMPORTANT!
Determine the gable end wall you want your
double doors on now.
Then, install this solid wall on opposite end.