Installation Guide

11
DOOR
• 3" Screw angled into 4x4.
• (2) at each point frame and
4x4 touch.
LEVELING & SQUARING A 10 x 8' FLOOR FRAME
• FOR 10' x 12', SKIP TO PAGE 12
FINISH
5
BEGIN
2
3
4
1
Use level and check the frame is level before applying floor panels.
Check for frame squareness by measuring diagonally across corners. If the
measurements are the same, the frame is square. The diagonal measurement
will be approximately 151-1/2" (385 cm).
When the frame is level and square, secure one side of frame to 4x4 runners using one fastener
at ends of each runner. At the opposite end of the frame, secure the frame to 4x4 runners with
one fastener at ends of each runner making sure the frame remains square (Fig. A).
Once the floor frame is level and square fasten the frame at each point the frame contacts the
4x4 runners (Fig. B). Go to page 15.
See page 9 for the preferred floor leveling method.
First, secure
at ends with
one fastener.
Second,
secure at
ends with
one fastener.
151-1/2"
(385 cm)
151-1/2"
(385 cm)
Fig. A
Fig. B
12"
(30,5 cm)
12"
(30,5 cm)
Runners are generally
12" (30,5 cm) from
ends of floor frame
and under seams.
LEVEL AND SQUARE FLOOR FRAME
Before attaching floor decking, it is important to level and square the floor frame.
A level and square floor frame is required to correctly construct your shed.
GABLE 10' x 8'
GABLE 10' x 12'