4
ADDITIONAL MATERIALS FOR BUILDING YOUR SHED
OPTIONAL MATERIALS
FOUNDATION
DRIP EDGE ..................... 40 Feet #15 ROOFING FELT
To cover 75 Sq. Ft. of r oof area.
1" GALVANIZED ROOFING NAILS.........1/4 Lb
For roofing felt.
REFER TO THE BACK OF THIS MANUAL AND THE MANUFACTURER’S INSTRUCTIONS
FOR INSTALLATION OF SHINGLES, DRIP EDGE AND FELT.
• This shed kit does not include a wood floor frame or floor panels. See pages 8 through 11 for suggested floor construction.
• It does not include ANY leveling materials.
•
See the FLOOR LEVELING section on page 7 for recommended methods and suggested materials to properly level your
floor, as this will vary depending on your specific site.
•
See the CONCRETE FOUNDATION section on page 3 for recommended m
ethods to build your shed on a poured concrete slab.
3-TAB SHINGLES ............................ 4 Bundles
PAINT FOR SIDING .......................... 2 Gallons
Use 100% acrylic latex exterior paint. (2) coats recommended.
CAULK ................................................. 2 Tubes
Use acrylic latex exterior caulk that is paintable.
1" GALVANIZED ROOFING NAILS.... 2 Lbs
For shingles.
PAINT FOR TRIM .............................1 Quart
Use 100% acrylic latex exterior paint.
WOOD GLUE ....................... Exterior Rated
REINFORCED WOOD FLOOR FRAME (OPTIONAL)
WOOD FLOOR FRAME (NOT INCLUDED)
IMPORTANT!
x2
x8
2 x 4 x 96” (5 x 10 x 243,8 cm)
2 x 4 x 96” (5 x 10 x 243,8 cm)
Treated Lumber
x9
Treated Lumber
x7
Cut to: 2 x 4 x 93" (5 x 10 x 236,2 cm)
2 x 4 x 93" (5 x 10 x 236,2 cm)
x2
2 x 4 x 92-5/8" (5 x 10 x 235,2 cm)
ea. 10D 3" (7,6 cm) Hot Dipped Galvanized Nails
FLOOR PANELS (NOT INCLUDED)
x106
x2
MATERIAL LIST: CUT LIST:
MATERIAL LIST: CUT LIST:
5/8 x 48 x 92-5/8" (1,6 x 122 x 235,2 cm)
x2
Depending on your specific use, you may want to construct a heavy
duty floor frame by adding additional floor joists. Below is a list in
addition to the framing materials above (not included):
x28
5/8 x 48 x 96” (1,6 x 122 x 243,8 cm) OSB Panels
10D 3” (7,6 cm) Hot Dipped Galvanized Nails
(Recommend 5/8” (1,6 cm) (minimum) thick OSB panels)
Use Treated Lumber For
Floor Framing
6D 2” (5,0 cm) Hot Dipped Galvanized Nails
Optional
12" (30,5 cm)
spacing