AssemblyInstructions

10
Solar Shed
Phoenix 10 x 4 Floor Extender Kit Instructions
Optional Floor Kit not supplied with Building Kit. Follow instructions
with Optional Floor Kit, they maybe different than this manual.
Note: Floor Kit parts are not stamped with identification letters.
2
2 - 2x4x24" Bond Boards
2 - 2x4x96" Bond Boards
6 - 2x4x42-1/2" Floor Joist
1 - 45-1/2"x96"x5/8" Floor Panels
1 - 23-7/8"x45-1/2"x5/8" Floor Panels
- 2" and 3" Nails
A
B
C
D
E
Parts Needed:
A
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
45-1/2"
(116 cm)
C C CCCC
A B
A B
Center of
Stud
Center of
Stud
Center of
Stud
Center of
Stud
120"
(305 cm)
10x8 Floor
Attach with
3" Nails
A:Position Bond Boards
& and Floor Joists
as shown.
Using 3” nails, nail twice
through each Bond Board
& into each end of each
Joist , keeping pieces
flush at top and ends, and
maintain 24” spacing as
shown. Where &
join together use 4-3” nails.
A
B
C
A
C
A
B
B
B
120"
(305 cm)
45-1/2"
(116 cm)
C
BA
2" Nails
(5 cm)
D
B: Position a 45-1/2” x 96” Floor Panel flush to the outside edges of sides and back of Floor Frame. Secure panel
with two 2” nails at outside corners and one 2” nail at other corners.
D
E
Nails every 12" (30 cm) through Floor Panels into all Floor Bond Boards and Floor Joists
E
C
D
24"
(61 cm)
24"
(61 cm)
48"
(122 cm)
2" Nails
(5 cm)
Original Floor
C: Position a 23-7/8” x 45-1/2” Floor Panel flush against first panel and flush to edges of Floor Frame. Secure
panel with two 2” nails at outside corners and one 2” nail at other corners.
Note: Mark a line on the Floor Panel over the center of each Floor Joist using a pencil and a piece of lumber from
the kit (or use a chalk line) to make nailing easier.
With Floor Panels flush to outside edges of Floor Frame, nail with 2” nails every 12” through Floor Panels into all
Floor Bond Boards and Floor Joists.
Your Floor is now complete. Check to be sure it is properly positioned and leveled to ground before beginning