STEP 26: RIDGE CAP (CONT'D)
INSTALL SECOND RIDGE CAP PER MANUFACTURER'S GUIDELINES AS SHOWN. (FIG. 4.4)
CONTINUE INSTALLING RIDGE CAP TO TOP OF ROOF UNTIL PEAK IS REACHED. (FIG. 4.5)
REPEAT PROCESS ON ALL RIDGES. (FIG. 4.5)
BAG # HARDWARE
15103 1" ROOFING NAIL X 175
INSTALL SECOND RIDGE CAP PER MANUFACTURER'S GUIDELINES AS SHOWN. (FIG. 4.4)
CONTINUE INSTALLING RIDGE CAP TO TOP OF ROOF UNTIL PEAK IS REACHED. (FIG. 4.5)
REPEAT PROCESS ON ALL RIDGES. (FIG. 4.5)
1" ROOFING NAIL
FIG. 4.4
X1 PER SIDE
PER MANUFACTURER'S
GUIDELINES
RIDGE CAP X 90
FIG. 4.5