Operation Manual

27
ENGLISH
GB
Inspection and maintenance plan
Regular servicing period Before any
start-up
If necessary Once a
week
After 6
months
Check that the planing blade is in perfect
condition
Inspection
Change
Check the function of the safety equipment
Inspection
Change
Clean dust and chips o the machine
Clean
Check the drive belt to ensure it has the
correct tension and is in good condition or
not worn
Inspection
Change
Oil or grease all moving connecting parts
Failure removal
Before rectifying a fault on the machine, switch o the machine and pull out the mains plug.
Failures
Causes
Removal
Machine does not work
or stops suddenly
• Power cut
• Motor or switch defective
• Check fuse, check overload switch on
machine.
• Have the motor or switch checked by
an electrician.
Machine stops during
planing
• Planing blade blunt/worn
• Overload switch has tripped
• Replace or sharpen blade
• Switch on the motor again once it has
cooled
Workpiece jams during
thicknessing
• Cutting depth too great • Reduce cutting depth and machine
the workpiece in several passes
Unsatisfactory surface
nish
• Planing blade blunt/worn
• Planing blade lled with chips
• Uneven feed
• Replace or sharpen blade
• Remove chips
• Feed the workpiece with constant
pressure and at reduced speed
Machined surface too
rough
Workpiece contains too much
moisture
• Dry workpiece
Machined surface cracked Workpiece was machined against the
grain
Too much material planed at one pass
• Machine the workpiece from the
opposite direction
• Machine the workpiece in several
passes
Workpiece speed too low
during thicknessing
Workpiece was machined against the
grain
Too much material planed at one pass
• Clean bench top and apply a thin
coating of lubricant wax
• Repair transport rollers
• Set the lever for the thicknessing
setting to the top position
Enable and check all safety equipment after all troubleshooting work.