User Guide

9
THIS UNIT MUST ONLY BE INSTALLED BY AN EXPERIENCED TECHNICIAN.
Preparation of the Gate
Before installing the GTO/PRO slide gate operator, make sure:
the gate is properly installed.
the gate is plumb, level, and moves freely.
the gate does not bind or drag on the ground.
the gate is screened if necessary (see page 5.)
roller guards are installed (see page 5.)
INSTALLING THE GATE OPERATOR
Overview of the Operator Installation
The diagram below is an example of a single slide gate installation with required safety features. The operator must
be installed on the inside of the gate. You must install safety edges (or photoelectric sensors) and roller guards
(not included) to reduce the possibility of bodily injury.
NOTE: A separate gate or entrance must be installed for pedestrian use.