User's Manual

FCC ID : U88GSTR-825DC-SPR
17/26
<Pic.9> Hole sizes of iDEN In-building RF Repeater
4.1.3 System set up
1) Once aforementioned process is done, open for service get ready.
2) For grounding, there is a grounding terminal in main power supply side and the grounding
terminal on a site and unit should be connected same.
3) System installation work is basically performed more than two people and should be careful for
unexpected accident.
4.1.4 Open for service
1) Check points before open
a. Verification of system installation status
Electricity, In/out antenna, coaxial cable connection, equipment mounts status.
b. Verification of system accessories
User should check whole necessary accessories.
c. Check receipt signal level
User should check whether receipt environmental condition is in accordance with system specification,
so that system operation will be optimized.
2) Check points after open