Installation Guide

EZ Standing Seam Roof
Mounting System
18 | P a g e
Minimum Panel Height
End Clamp Attachment
Mid Clamp Attachment
There must be a minimum of 1.5 inches of Rail
extending beyond the PV panel frame.
Clamp the PV panel frame by inserting the T-
Bolt into the Rail slot. Position the End Clamp
firmly against the PV panel frame and secure
using the 1/4-20 Collar Bolt. Using a 7/16”
socket, torque to 7.5 ft. lbs.
Insert the T-Bolt in the Rail slot and turn
clockwise 90° to engage the head into the slot.
Insert Grounding T-Bolt Holder to lock T-Bolt in
place.
Thread the 1/4-20 Collar Bolt onto the top of the
T-Bolt as shown. After positioning the Mid
Clamp firmly against the PV panel frame, using
a 7/16” socket, tighten to 7.5 ft. lbs.
Minimum leading edge height to meet a
UL1703 PV module fire standard is 3 inches.
3 inch minimum
from bottom of PV
module frame to the
roof covering
Adjacent solar
panel has been
removed for
clarity