Installation Guide
Applications
975-0289-01-01 1–9
Combination Applications
Important:
Installations of this kind must be certified/approved as
“code-compliant” to the national and local building and electrical codes.
Installers should have adequate knowledge of national and local code to ensure
the installation passes inspection by the local electric authority.
Figure 1-8
Hardwired Combination Applications
Wind Turbine
(Must have its own
charger controller)
DC IN
AC OUT
AC IN
AC Distribution
Panel
(Sub-Panel)
Solar Panel(s) and
Charge Controller(s)
Main AC
Distribution
Panel
DC IN
DC Disconnects
(recommended)
Important:
The
combination of loads
cannot exceed 1440 W.
Run-times will depend on
the amp-hour rating of
the batteries.
Example only.
Actual installation may vary.
975-0289-01-01(PowerHub_1800_IG).book Page 9 Thursday, June 4, 2015 9:49 AM