4. 60'-105' Bin Manager Temperature Cable Bracket Instructions
PNEG-1840 60'-105' Bin Manager Temperature Cable Support Bracket Instructions 17
75' Temperature Cable Support Assembly
Figure 4F
Installation instructions: Attach left and right bracket assemblies to roof beams as shown in detail 10 on Page 18.
Adjust bracket position along the roof beam to the desired radius. Attach support channel to the left and right bracket
assemblies with 3/8" x 1-1/2" flange head bolts, washers and nuts. Attach hanging bracket to the support channel with
3/8" x 1-1/2" flange head bolts, washers and nuts. Tighten all 1/2" bolts to a minimum torque of 120 ft. lbs.
Left bracket assembly
(See detail 10 on Page 18.)
Right bracket assembly
(See detail 10 on Page 18.)