User's Manual
Setup
22 3A2347T
NOTE: If using a 480V to 240V transformer, the breaker
size entered will be two times the 480V rating. If using
transformer 24U169, the breaker size should be set to
30 amps and power type should be set to single phase.
NOTE: The InvisiPac system limits the amount of power
it pulls based on the input circuit breaker size. This
impacts the startup times because it affects the heating
energy used to warm up the materials.
b. Select the incoming power type.
5. On the Advanced 1 screen, set the system date and
time.
6. On the Advanced 2 screen, set the temperature and
mass units.
7. To setup the optional Schedule function, see
Schedule on page 29.
NOTE: The Schedule function enables the system to
automatically enable and disable heating at specified
times so that the system is already up to temperature
when a shift begins.
8. If desired, set any remaining settings in the Setup
screens before going on to the next steps that use
the Operation screens. These are not required for
system operation but include useful functions. See
Appendix A - ADM, beginning on page 104, for
detailed information about each setup item.
9. Press to switch from the Setup screens to the
Operation screens. Use , , , and to
navigate between screens.
10. On the Targets screen, use and , shown
next to , to adjust system melter setting.
Also, the desired temperature setting can be typed
in using the numeric keypad.