User's Manual

Calibration
18 3A1657F
38. Prepare dispense valve:
For GX7-DI Dispense Valves --
a. Close off material flow to the dispense head for
BOTH chemicals. Turn the valve on the coupling
block manifold fully clockwise until tight.
b. Remove and clean the mixing module retainer.
c. Remove and clean the mix module. The dis-
pense valve can be manually cycled open and
closed by pressing the dispense valve button on
the Maintenance screen. Cycle open and
closed once to pull the module partially off of
the valve rod.
d. Remove the inlet screen and check valve
assembly for the chemical side that was NOT
being calibrated and inspect for cross contami-
nation of chemical.
e. Remove manifold and completely clean if cross-
over is found. Clean parts with solvent or
replace as necessary.
f. Return to step 8 and repeat calibration steps for
the other chemical side.
For L-Head, S-Head, and GX-16 Dispense Valves
Only --
a. Remove blocked orifice and replace with origi-
nal orifice.
b. Clean the used blocked orifice for future use.
c. Go to step 27 to repeat procedure to calibrate
the other material line.
For Fusion and EP Guns Only --
a. Remove the ratio check assembly and clean for
future use.
b. Attach fluid manifold to gun.
For Probler P2 Gun Only --
a. Remove material lines from calibration kit.
b. Remove calibration kit and clean for future use.
c. Attach material lines to gun.
For MD2 Valve Only --
a. Remove ratio check nozzle and clean for future
use.
b. Install static mixer.
All Assemblies --
39. Navigate to the System 3 screen then update the
Alarm % value to the desired percent.