User's Manual
Startup
24 313876F
Startup
1. Lubricate the metering rod ports in the oil cup
retaining block and fill the spool valve ports with
compatible lubricant. Consult with your material
supplier to select an acceptable lubricant. Regularly
verify that lubricant is present.
2. Perform Ratio Check, page 26.
3. Install mixer and shroud.
4. Pressurize the A and B material feed systems con-
nected to the metering valve to prime the system.
See page 3 for maximum inlet feed pressures.
5. Dispense several full stroke shots until material is
air-free and has good shut-off at the nose.
NOTE: Very viscous, compressible materials may con-
tinue to droll after system is primed. Reduce flow rate as
required to produce air-free dispense.
NOTE: Very thin materials may require tilting the valve
greater than 45 degrees and dispensing shots until
material is air-free. Remove oil from cups before pro-
ceeding.
NOTICE
Testing has shown that failure to lubricate the valve
will significantly reduce seal life.
F
IG. 11: Top View of Metering Valve with Top Section
Removed
Metering Rod Ports
Spool Valve Ports