Profile C ramps up to 82% of the full cooling demand airflow
and operates there for approximately 7 1/2 minutes. The
motor then steps up to the full demand airflow. Profile C
also has a one (1) minute 100% OFF delay.
100% CFM
OFF
OFF
Figure 17 - Profile C
Profile D ramps up to 50% of the demand for 1/2 minute,
then ramps to 82% of the full cooling demand airflow and
operates there for approximately 7 1/2 minutes. The motor
then steps up to the full demand airflow. Profile D has a 1/
2 minute at 50% airflow OFF delay.
OFF
OFF
Figure 18 - Profile D
7. If an electric heater kit has been installed, determine the
heater kilowatt (kW) rating. Find the heater size in the table
below. Set dipswitches 9, 10, and 11 for the installed heater
as shown in the table below. The adjust setting (already
established by the cooling speed selection) also applies to
the electric heater kit airflow. Thus, the electric heater airflow
is adjusted by the same amount. Verify selected CFM by
counting the green CFM LED blinks.
If an electric heater kit has not been installed, set dip switches
9, 10, and 11 to any valid heater kit setting (see airflow table
for valid settings). This will prevent an Ec Error code from
being displayed.