GMVC9 GCVC9 Installation Instructions

9
If this furnace is to be installed in the same space with other
gas appliances, such as a water heater, ensure there is an ad-
equate supply of combustion and ventilation air for the other
appliances. Refer to the latest edition of the National Fuel Gas
Code NFPA 54/ANSI Z223.1 or CAN/CSA B149.1-15 Installation
Codes or applicable provisions of the local building codes for
determining the combustion air requirements for the appliances.
Most homes will require outside air be supplied to the furnace
area by means of ventilation grilles or ducts connecting directly
to the outdoors or spaces open to the outdoors such as attics or
crawl spaces.
I
NSTALLATION
P
OSITIONS
This furnace may be installed in an upright position or horizon-
tal on either the left or right side panel. Do not install this
furnace on its back. For upright upflow furnaces, return air
ductwork may be attached to the side panel(s) and/or basepan.
For horizontal upflow furnaces, return air ductwork must be
attached to the basepan. For both upright or horizontal
counterflow furnaces, return ductwork must be attached to the
basepan (top end of the blower compartment). NOTE:
Ductwork
must never be attached to the back of the furnace. Contact
your distributor for proper airflow requirements and number of
required ductwork connections. Refer to “Recommended In-
stallation Positions” figure for appropriate installation positions,
ductwork connections, and resulting airflow arrangements.
H
ORIZONTAL
A
PPLICATIONS
& C
ONSIDERATIONS
2" 2" 3/8"
ANGLE
IRON
(3
PLACES
)
XX
Figure 2
When installing a furnace horizontally, additional consideration
must be given to the following:
FURNACE SUSPENSION
If suspending the furnace from rafters or joists, use 3/8" threaded
rod and 2”x2”x1/8” angle iron as shown in the following dia-
gram. The length of rod will depend on the application and the
clearances necessary.
If the furnace is installed in a crawl space it must be suspended
from the floor joist or supported by a concrete pad. Never install
the furnace on the ground or allow it to be exposed to water.
FRONT COVER PRESSURE SWITCH TUBE LOCATION
When a furnace is installed horizontally with left side down
the front cover pressure switch tube must be re-located to
the lower port of the collector box cover.
1. Remove tube from front cover pressure switch and
collector box cover.
2. Remove rubber plug from bottom collector box port
and install on top collector box port.
3. Locate 24” x 1/4” tube in bag assembly.
4. Install one end on front cover pressure switch.
5. Route tube to lower port on collector box cover and
cut off excess tubing.
DRAIN TRAP AND LINES
In horizontal applications the condensate drain trap is secured to
the furnace side panel, suspending it below the furnace. A mini-
mum clearance of 5 ½” below the furnace must be provided for
the drain trap. Additionally, the appropriate downward piping
slope must be maintained from the drain trap to the drain loca-
tion. Refer to Condensate Drain Trap and Lines for further de-
tails. If the drain trap and drain line will be exposed to tempera-
tures near or below freezing, adequate measures must be taken
to prevent condensate from freezing.
LEVELING
Leveling ensures proper condensate drainage from the heat ex-
changer. For proper flue pipe drainage, the furnace must be
level lengthwise from end to end. The furnace should have a
slight tilt from back to front with the access doors downhill
from the back panel approximately 1/2 to 3/4 inches. The
slight tilt allows the heat exchanger condensate, generated in
the recuperator coil, to flow forward to the recuperator coil front
cover.
ALTERNATE VENT/FLUE AND COMBUSTION AIR CONNECTIONS
In horizontal installations provisions for alternate flue and com-
bustion air piping are available for upflow furnaces with left dis-
charge and counterflow furnaces with right air discharge. This
configuration allows the flue and combustion air piping to be run
vertically through the side of the furnace. Refer to the “Recom-
mended Installation Positions” figure for further detail. The stan-
dard piping connections may also be used in these positions.
Refer to Vent/Flue Pipe and Combustion Air Pipe for details con-
cerning the conversion to the alternate vent/flue and combus-
tion air connections.
When using the horizontal alternate vent configuration, you must
use the RF000142 vent drain kit. See following illustration.