GMVC9 GCVC9 Installation Instructions

17
VENT/FLUE PIPE TERMINATIONS
12" MIN. ABOVE
HIGHEST ANTICIPATED
SNOW LEVEL
12" MIN.
V
ENT/FLUE TEE (
or
45° ELBOW
TURNED DOWN or
90° ELBOW TURNED
DOWN
OPTIONAL)
Horizontal Termination (Single Pipe)
Above Highest Anticipated Snow Level
Figure 15
NOTE: If either a 90 degree or 45 degree elbow is used for
termination, it must be pointed downward.
The vent/flue pipe may terminate vertically, as through a roof,
or horizontally, as through an outside wall.
Vertical vent/flue pipe terminations should be as shown in the
following figure. Refer to Vent/Flue Pipe and Combustion Air
Pipe - Termination Locations for details concerning location re-
strictions. The penetration of the vent through the roof must be
sealed tight with proper flashing such as is used with a plastic
plumbing vent.
Horizontal vent/flue pipe terminations should be as shown in
the following figure. Refer to Vent/Flue Pipe and Combustion
Air Pipe. To secure the pipe passing through the wall and pro-
hibit damage to piping connections, a coupling should be in-
stalled on either side of the wall and solvent cemented to a length
of pipe connecting the two couplings. The length of pipe should
be the wall thickness plus the depth of the socket fittings to be
installed on the inside and outside of the wall. The wall pen-
etration should be sealed with silicone caulking material.
NOTE: Terminate both pipes in the same pressure zone
(same side of roof, no major obstacles between pipes,
etc.).
90º OR 4
ELBOW
12" MIN. TO GRADE OR
HIGHEST ANTICIPATED
SNOW LEVEL
6” MAX
4” MIN
Standard Horizontal Terminations (Dual Pipe)
Figure 16
DIRECT VENT (DUAL PIPE) PIPING
Direct vent installations require both a combustion air intake
and a vent/flue pipe. The pipes may be run horizontally and exit
through the side of the building or run vertically and exit through
the roof of the building. The pipes may be run through an exist-
ing unused chimney; however, they must extend a minimum of
12 inches above the top of the chimney. The space between the
pipes and the chimney must be closed with a weather tight,
corrosion resistant flashing. Both the combustion air intake and
a vent/flue pipe terminations must be in the same atmospheric
pressure zone. Refer to Vent/Flue and Combustion Air Pipe -
Termination Locations or Concentric Vent Termination for spe-
cific details on termination construction. For details concerning
connection of pipes to the furnace, refer to the Vent/Flue Pipe
and Combustion Pipe - Standard Furnace Connections or Alter-
nate Furnace Connections.
Alternate Horizontal Vent Termination (Dual Pipe)
Figure 17
90°
ELBOWS
12" MIN. ABOVE
HIGHEST ANTICIPATED
SNOW LEVEL
3” - 24”