CAPF Installation Manual

4
If the uncased coil is to be installed on top of a gas furnace,
allow enough space between the top to the furnace and the
bottom of the plastic coil drain pan to have a free flow of air.
A minimum of 2.0" distance from the top of the furnace and the
bottom of the coil pan is required.
NOTE: The coil must be installed with the line set and drain
openings to the front of the furnace.
X
2"
GAS FURNACE
OR
COIL
SUPPORT
FIELD FABRICATED SUPPORT
FOR UNCASED COILS
BOTTOM FLANGE
DETAIL CAN BE
TYPICAL OF THE
DETAILS BELOW
X = COIL PAN WIDTH
+ INSULATION THICKNESS X 2
Figure 4
NOTE: Water coming from the secondary line means the coil
primary drain is plugged and needs immediate attention.
Install a trap in the drain line below the bottom of the drain pan
(Figure 5). If using a copper drain line, solder a short piece of
pipe, minimum 6” length, to the connector before installing a
drain fitting.
DO NOT over torque the 3/4” copper connector to the plastic
drain connection. Using a wet rag or heatsink material on the
short piece to protect the plastic drain pan, complete the drain
line installation. Use Figure 6 as a template for typical drain
pipe routing. This figure shows how to avoid interference with
vent piping.
2” MIN.
3” MIN.
Figure 5
80.0% FURNACE 92.6% FURNACE
92.6% FURNACE
Figure 6
11. Return Ductwork
DO NOT TERMINATE THE RETURN DUCTWORK IN AN
AREA THAT CAN INTRODUCE TOXIC OR OBJECTIONABLE
FUMES/ODORS INTO THE DUCTWORK.
NOTE: SPECIFICATIONS AND PERFORMANCE DATA LISTED HEREIN ARE SUBJECT TO CHANGE WITHOUT NOTICE
5151 San Felipe, Suite 500, Houston, TX 77056
© 2005-2006, 2012-2013 Goodman Manufacturing Company, L.P.
Visit our website at www.daikincomfort.com, www.goodmanmfg.com or www.amana-hac.com for information on:
Products
Warranties
Customer Services
Parts
Contractor Program and Training
Financing Options
is a registered trademark of Maytag Corporation or its related companies and is used under license. All rights reserved.