MPPT-PRO-60 Manual

gpelectric.com | [page 29]
INSTALLATION
7.3.2 ORDER OF CONNECTION
1. Connect the battery rst, then the solar panel and nally the load. Follow the “+” and “-” pole connection mode.
2. Connect the MAIN controller rst, then connect to the next AUXILLARY controller followed by the battery, solar panel
and lastly, the controller according to the ID.
7.3.3 INTERFACE DEFINITION
RS485 INTERFACE
NO. DEFINITION PARALLEL OPERATION
12V
GND Black
D- Yellow
D+ Red
RS485 WIRING DIAGRAM (PARALLEL OPERATION)
7.3.4 PARAMETER SETTING
IN-SET MENU
1.
ADDRESS: the ID of the MAIN must be minimal, followed by the number from the machine to the large set.
For example, the MAIN ID is set to number 1, the AUXILLARY ID of the second controller is set to number 2 and the
AUXILLARY ID of a third one would be set to 3.
1 2 3 4
1
2
3
4
AUTO/SLD
BST : 14.4V
LVD : 11.0V
SET