12.7.5 Resetting parameters
This feature allows you to reset the parameters of the control
unit (factory setting).
b
The resetting of factory settings is irreversible.
Any customised conguration of the control unit
will be lost.
• Using the buttons ,
select Settings reset on the screen.
• Press the button
to conrm.
• Increase or decrease with the
buttons to display the
desired value.
• Press the button
to conrm.
• Press the button
.
12.8 Commissioning
This menu allows you to carry out the necessary operations on
the appliances following installation.
• Using the buttons , select
Commissioning on the screen.
• Press the button
to conrm.
12.8.1 Filling the heating circuit
i
The Systempro control unit is used to open the
valves of each zone during lling, if more than one
heating zone is installed.
• Select Fill htg circuit on the screen
using the buttons .
• Press the button
to conrm.
The screen shows the pressure
measured in the system.
• Activate lling mode by pressing the
button
.
• Refer to the boiler instructions for
lling the boiler.
The screen displays the pressure
measured in the system and that
installation lling is in progress.
• To stop lling press the button
.
• Close the lling loop.
• Press the button
to conrm.
12.8.2 Venting the heating circuit
Venting of the heating circuit enables the purging of any air in
the heating circuit.
• Using the buttons ,
select Air venting on the screen.
• Press the button
to conrm.
• Open the different heating circuit air vent.
• Using the buttons ,
select Vent heating circuit on the
screen.
• Press the button
to conrm.
• Conrm with the button in
order to begin the venting process.
The venting process is carried out for
15 minutes. You can simultaneously run
the venting of the HP circuit.
• Press the button
.
b
When venting is complete, close the different
heating circuit air vent.