Tub Installation Guide
4
G i a g n i
SUMMARY OF INSTALLATION PROCESS:
Step 1 - PREPARE THE SITE
NOTICE: Shut off hot and cold water. Make sure the oor will support 1200 lbs.
Position the plumbing according to the roughing-in information. Cap the supplies and check for leaks.
Make sure the drain location corresponds to the bath outlet.
Step 2 - PREPARE THE TUB
CAUTION: Risk of personal injury. Obtain sufcient help to carefully lift or move the tub.
Level the bath as needed with adjusters on appropriate feet.
The bath must be resting evenly. Verify the bath is level across the top and along the drain side.
Step 3 - INSTALL THE FEET/TUB BASE (see page 5)
Step 4 - INSTALL THE DRAIN (see page 11)
Step 5 - INSTALL THE FAUCET (see page 12)
ROUGHING-IN and SPECS (see page 25)
NOTE: Make sure a watertight seal exists on all bath drain connections.
Provide access to all plumbing connections to simplify future maintenance.