6. Installation
This section describes the steps to be followed to physically install the Node B.
The Rack Mount installation has 2 basic physical configurations V4A or V4B/V4C
Installation. Note while there is different functionality between V4B and C the physical
configuration is the same.
This section shall describe both configurations.
Step 1 Pre-Installation
The following are the initial checks that should be carried out to ensure that preparation for
the installation is complete.
For Installation Check Card please see Appendix A at the back of this manual.
1. Review site construction drawings to determine if site was constructed
according to the drawings.
2. Review drawings and actual installation to determine location of Node B
installation.
3. Check availability of electrical, grounding and antenna connections.
4. Complete site survey.
5. Check structural strength of mounting rack or frame including shelves/rails to
support Node B total weight of 35kgs (77lbs) or multiples if a multi-sector
installation.