9
With the generator running and loads powered by generator AC
output, turn ON the utility power supply to the transfer switch. The
following should occur:
• After approximately 15 seconds, the switch should transfer
loads back to the utility power source.
• Approximately one minute after re-transfer, the engine should
shut down.
With the generator in the AUTOMATIC mode, the system is now set
for fully automatic operation.
3.6 TESTING OVERLOAD
PREVENTION CONTROL BOARD
(OPCB)
A Test pushbutton is provided on the bottom of the OPCB to test
the operation of the tested functions. The Test button will work
when the ATS is in the Utility or the Generator position.
1. Turn the Utility supply on to the ATS.
2. Press the TEST pushbutton on the OPCB.
3. Verify that all of the connected loads to be “shed” become
disabled. The method of verification will depend on the type
of load.
4. After five (5) minutes verify AC 1 and Load 1 are energized
Status LED AC 1 and Load 1 is ON.
5. After another 15 seconds, verify AC 2 and Load 2 are ener-
gized Status LED AC 2 and Load 2 are ON.
6. After another 15 seconds, verify Load 3 is energized Status
Load 3 is ON.
7. After another 15 seconds, verify Load 4 is energized Status
Load 4 is ON.
3.7 INSTALLATION SUMMARY
1. Ensure that the installation has been properly performed as
outlined by the manufacturer and that it meets all applicable
laws and codes.
2. Test and confirm proper operation of the system as outlined
in the appropriate installation and owner’s manuals.
3. Educate the end-user on the proper operation, maintenance
and service call procedures.
Important! If the end user ever finds it necessary to turn the
generator off during prolonged utility outages to conserve on
fuel, educate them on these simple, but important steps:
To turn the generator OFF (while running in AUTO and online):
1. Turn OFF (or OPEN) the main Utility disconnect.
2. Turn OFF (or OPEN) the Main Line Circuit Breaker (MLCB) on
the generator.
3. Turn the generator OFF.
To turn the generator back ON:
1. Put the generator back into AUTO and allow to start and
warm-up for a few minutes.
2. Turn ON (or CLOSE) the MLCB on the generator.
The system will now be operating in its automatic mode. The main
utility disconnect can be turned ON (or CLOSED), but to shut the
unit off, this complete process must be repeated.
9
Operation