Install Manual
Table Of Contents
- Table of Contents
 - Section 1: Safety
 - Section 2: General Information
 - Section 3: Installation
 - Section 4: Operation
 - Section 5: Drawings and Diagrams
- Installation Drawing—100A SE & Non-SE/150-200A Non-SE
 - Installation Drawing—150/200A SE
 - Installation Drawing—Liquid Cooled Generator
 - Installation Drawing—Liquid-Cooled Generator
 - Installation Drawing—Air-Cooled Generator SE and Non-SE Rated ATS
 - Installation Drawing—Air-Cooled Generator SE and Non-SE Rated ATS
 
 
Operation
Automatic Transfer Switch Owner’s Manual 19
5. Set  the  generator  main  circuit  breaker  to  ON  or
CLOSED.  The  generator  now  powers  all  LOAD
circuits.  Check generator operation  under load  as
follows:
• Turn  on  electrical  loads  to  the  full  rated
wattage/amperage  capacity  of  the  generator.
DO NOT OVERLOAD.
• With  maximum  rated  load  applied,  check
voltage  and  frequency  across  transfer  switch
terminals  E1  and  E2.  Voltage  should  be
greater  than  230  VAC  (240  VAC  system);
frequency should be greater than 59 Hz.
• Verify  that  the  gas  pressure  remains  within
acceptable  parameters  (see  the  generator
Installation manual).
• Let  the  generator  run  under  rated  load  for  at
least 30 minutes. With  unit running, watch for
unusual  noises,  vibration,  or  overheating  that
might indicate a problem.
6. When  checkout  under  load  is  complete,  set  main
circuit  breaker  of  the  generator  to  the  OFF  or
OPEN position.
7. Let the generator run at no-load for several minutes.
Then, shut down by selecting the OFF mode.
8. Move  the  main  switch  contacts  back  to  the  utility
position. 
NOTE:  See  Manual  Operation.  Handle  and  operating
lever of transfer switch should be in down position.
9. Set the utility service disconnect circuit breaker of
the transfer switch to ON or CLOSED.
10. The system is now set for fully automatic operation.
Checking Automatic Operation
To  check  the  system  for  proper  automatic  operation,
proceed as follows:
1. Verify generator is OFF.
2. Set the utility service disconnect circuit breaker of
the transfer switch to OFF or OPEN.
3. Verify switch is de-energized.
4. Install front cover of the transfer switch.
5. Set the utility service disconnect circuit breaker of
the transfer switch to ON or CLOSED.
6. Set the generator main circuit breaker to ON.
7. On the generator panel, select AUTO. The system
is now ready for automatic operation.
8. Set the utility service disconnect circuit breaker of
the transfer switch to OFF or OPEN.
With  the  generator  ready  for  automatic  operation,  the
engine  should  crank  and  start  when  the  utility  source
power  is  turned  OFF  after  a  five  second  delay  (factory
default setting). After starting, the transfer switch should
connect load circuits  to the standby side after a  five (5)
second warm-up  delay.  Let the system  operate  through
its entire automatic sequence of operation.
NOTE:  Timer  durations  may  differ  between  generators
and settings.
With  the  generator  running  and  loads  powered  by
generator  AC  output,  set  the  utility  service  disconnect
circuit breaker of the transfer switch to ON or CLOSED.
The following should occur:
• After  approximately  15  seconds,  the  switch  should
transfer loads back to the utility power source.
• Approximately  one  minute  after  re-transfer,  the
generator should shut dow
n
.
With the generator in the AUTOMATIC mode, the system
is now set for fully automatic operation.
Installation Summary
1. Verify the installation has been properly performed
as outlined by the manufacturer and that it meets
all applicable laws and codes.
2. Verify proper operation of the system as outlined in
the appropriate installation and owner’s manuals.
3. Educate  the  end-user  on  the  proper  operation,
maintenance and service call procedures.
NOTE:  The Utility Power Circuit Breaker in  the transfer
switch must  be  turned  OFF  to simulate  a utility outage.
Shutting off the main disconnect in a subpanel connected
to the transfer switch will NOT simulate an outage. 
Shutting Generator Down While 
Under Load or During a Utility Outage
IMPORTANT  NOTE:  To  avoid  equipment  damage,  fol-
low these steps, in order, during utility outages. Shut-
downs  may  be  required  during  utility  outages  to
perform routine maintenance or to conserve fuel.
To turn generator OFF:
1. Set utility MLCB to OFF (OPEN).
2. Set  generator  MLCB  (generator  disconnect)  to
OFF (OPEN).
3. Allow  generator  to  run  for  cool-down  for  approxi-
mately one minute.
4. Set generator to OFF at the controller.
5. Remove 7.5A fuse from controller.
To turn generator back ON:
1. Install 7.5A fuse in controller.
Automatic start-up. Disconnect utility power and 
render unit inoperable before working on unit. 
Failure to do so will result in death or serious injury.
(000191)
DANGER










