Operating Guide
Operation
Automatic Transfer Switch Owner’s Manual 13
5. Set generator MLCB to ON (CLOSED). Generator 
now  powers  all  LOAD  circuits.  Verify  generator 
operation under load as follows:
• Turn  on  electrical  loads  to  the  full  rated  watt-
age/amperage capacity of generator. DO NOT 
OVERLOAD.
• With maximum rated load applied, check volt-
age  and  frequency across transfer switch ter-
minals  E1  and  E2.  Voltage  should  be  greater 
than 230 VAC (240 VAC system); frequency 
should be greater than 59 Hz.
• Verify fuel pressure remains within acceptable 
parameters  (see  generator  installation  man-
ual).
• Allow generator to run under rated load for at 
least 30 minutes. With unit running, inspect for 
unusual  noises,  vibration,  or  overheating  that 
might indicate a problem.
6. Set  generator  MLCB  to  OFF  (OPEN)  when  test 
under load is complete.
7. Allow generator to run at no-load for several min-
utes. Then, shut down generator by pressing OFF.
8. Set main switch contacts to utility. 
NOTE:  See  Manual Operation.  Handle  and  operating 
lever of transfer switch should be in down position.
9. Set  utility  service  disconnect  circuit  breaker  of 
transfer switch to ON (CLOSED).
System is now set for fully automatic operation.
Checking Automatic Operation
Proceed as follows to check system for correct automatic 
operation:
1. Verify generator is in OFF mode.
2. Set utility service disconnect circuit breaker of the 
transfer switch to OFF (OPEN).
3. Verify switch is de-energized.
4. Install front cover of transfer switch.
5. Set transfer switch utility service disconnect circuit 
breaker to ON (CLOSED).
6. Set generator MLCB to ON.
7. Select AUTO on generator control panel. System is 
now ready for automatic operation.
8. Set transfer switch utility service disconnect circuit 
breaker to OFF (OPEN).
With  generator  ready  for  automatic  operation,  engine 
should crank and start when utility source power is turned 
off after a five second delay (factory default setting). After 
starting,  transfer  switch  should  connect  load  circuits  to 
standby  side after  a  five  second  delay. Allow  system  to
operate through entire automatic sequence of operation.
With generator running and loads powered by generator 
AC  output,  set  transfer  switch  utility  service  disconnect 
circuit breaker to ON (CLOSED). The following will occur:
• After  approximately  15  seconds,  transfer  switch  will 
transfer loads to utility power source.
• Approximately  one  minute  after  transfer,  generator 
should shut down.
With generator in AUTOMATIC mode, system is now set 
for fully automatic operation.
Installation Summary
1. Verify installation has been performed correctly as 
outlined by the  manufacturer  and that  it  meets  all 
applicable laws and codes.
2. Test and verify correct operation of the system as 
outlined in the appropriate installation and owner’s 
manuals.
3. Educate  end-user  on  correct  operation,  mainte-
nance, and service call procedures. 
NOTE: The utility power circuit breaker in transfer switch 
must be turned OFF to simulate a utility outage. Shutting 
off main disconnect in a subpanel connected to transfer 
switch will NOT simulate an outage. 
Shutting Generator Down While 
Under Load
IMPORTANT NOTE: To avoid equipment damage, fol-
low these steps, in order, when shutting the genera-
tor  down  during  utility  outages.  Shutdowns  may  be 
required  during  outages  to  perform  routine  mainte-
nance or to conserve fuel.
To  turn  generator  OFF  (while  running  in AUTO  and 
online):
1. Turn main utility disconnect off.
2. Turn  generator  MLCB  (generator  disconnect)  to 
OFF (OPEN).
3. Run  generator  for  approximately  one  minute  to 
cool down.
4. Turn generator OFF.
To turn generator back ON:
1. Put  generator  into  AUTO  mode.  Start  generator 
and warm-up for a few minutes.
2. Set  MLCB  (generator  disconnect)  to  ON 
(CLOSED).
The system now operates in AUTO mode. The main util-
ity disconnect can be turned ON (CLOSED). To shut unit 
off, repeat this complete process.










