Product Manual

Table Of Contents
Operation
12 Automatic Transfer Switch Owner’s Manual
Return to Utility Source Side
1. Manually actuate switch to return manual operating
handle to the UP position.
2.
Remove manual operating handle from movable
contact carrier arm. Return handle to storage bracket.
Voltage Checks
NOTE: Use the Digital Multimeter (DMM) LowZ low input
impedance setting to collect accurate voltage
measurements. LowZ eliminates the possibility of
inaccurate ghost voltage readings, also known as
phantom voltage or stray voltage readings. Refer to the
DMM manufacturer’s literature for additional information.
Utility Voltage Checks
1. Turn ON the UTILITY power supply to the transfer
switch using the breaker in main distribution panel.
2. With an accurate AC voltmeter, check for correct
voltage. Measure across ATS terminal lugs N1 and
N2; N1 to NEUTRAL and N2 to NEUTRAL.
Generator Voltage Checks
1. On the generator panel, select the MANUAL mode
of operation. The generator should crank and start.
2. Let the generator stabilize and warm up at no-load
for at least five minutes.
3. Set the generator's main circuit breaker (CB1) to its
ON or CLOSED position.
4. With an accurate AC voltmeter and frequency
meter, check the no-load, voltage and frequency.
Measure across ATS terminal lugs E1 to E2; E1 to
NEUTRAL and E2 to NEUTRAL
.
5. When certain that generator supply voltage is
correct and compatible with transfer switch ratings,
turn OFF the generator supply to the transfer
switch.
6. Set the generator main circuit breaker (CB1) to
OFF or OPEN.
7. On the generator panel, select the OFF mode to
shut down the generator.
NOTE: Do NOT proceed until generator AC output
voltage and frequency are correct and within stated
limits.
Generator Tests Under Load
1. Set the generator main circuit breaker to OFF or
OPEN.
2. Set the utility service disconnect circuit breaker to
OFF or OPEN.
3. Manually actuate the transfer switch main contacts
to the emergency (Standby) position. See Manual
Operation.
4. To start the generator, select the MANUAL mode of
operation. When engine starts, let it stabilize for a
few minutes.
5. Set the generator main circuit breaker to ON or
CLOSED. The generator now powers all LOAD
circuits. Check generator operation under load as
follows:
Turn on electrical loads to the full rated wattage/
amperage capacity of the generator. DO NOT
OVERLOAD.
With maximum rated load applied, check voltage
and frequency across transfer switch terminals E1
and E2. Voltage should be greater than 230 VAC
(240 VAC system); frequency should be greater
than 59 Hz.
Verify that the gas pressure remains within
acceptable parameters (see the generator
Installation Guidelines manual).
Let the generator run under rated load for at least
30 minutes. With unit running, listen for unusual
noises, vibration, overheating, etc., that might
indicate a problem.
6. When checkout under load is complete, set main
circuit breaker of the generator to the OFF or
OPEN position.
7.
Let the generator run at no-load for several minutes.
Then, shut down by selecting the OFF mode.
(000129)
DANGER
Electrocution. High voltage is present at
transfer switch and terminals. Contact with live
terminals will result in death or serious injury.
(000123)
DANGER
Electrocution. Turn utility supply OFF before
working on utility connections of the transfer
switch. Failure to do so will result in death or
serious injury.
(000129)
DANGER
Electrocution. High voltage is present at
transfer switch and terminals. Contact with live
terminals will result in death or serious injury.
Frequency 60-62 Hz
Terminals E1 to E2 240-246 VAC
Terminals E1 to NEUTRAL 120-123 VAC
Terminals E2 to NEUTRAL 120-123 VAC