Installation Instructions
3
1. Plan the generator location.
NOTE:
For the generator installation, utilize the standby generator
installation and owner's manuals. Ensure that the distance from
the structure (Minimum 18 " inches) allows for slack in the five
foot pre-wired liquid tight conduit and that it meets the code.
2. Determine where the flexible conduit will pass through the build-
ing from inside to outside. When certain there is clearance on
each side of the wall, drill a small pilot hole through the wall to
mark the location. Drill an appropriate sized hole through the
sheathing and siding with hole saw.
3. While adhering to all local electrical codes, route the 30 foot
conduit along ceiling/floor joists and wall studs to the location
where the conduit will pass through the wall to the exterior of the
building.
NOTE:
The 30 foot flexible conduit can be lengthened a maximum of 15
additional feet using the same conductor size and conduit diam-
eter. The lengthening must comply with local, state and/or fed-
eral codes. The splice point must be in an approved junction box
per code. The 2 foot and 5 foot conduit cannot be lengthened.
Typical Standby Generator Placement
Drill Hole Through House
2
Drill Pass Through Hole
3
Drill appropri-
ate sized hole
Drill appropri-
ate sized hole
Residential Transfer Switch Installation Guide