Installation Guide

Control Panel Start-Up/Testing
Installation Guidelines For Australian 50 Hz Air-Cooled Generators 39
Before starting, complete the following:
1. Verify generator is OFF.
2. Set the generator main circuit breaker to OFF
(OPEN).
3. Turn OFF all breakers that will be powered by the
generator.
4. Check the engine crankcase oil level and, if neces-
sary, fill to the dipstick FULL mark with the recom-
mended oil. Do not overfill.
5. Check the fuel supply. Gaseous fuel lines must
have been properly purged and leak tested in
accordance with applicable fuel-gas codes. All fuel
shutoff valves in the fuel supply lines must be
open.
NOTE: During initial start up only, the generator may
exceed the normal number of start attempts and experi-
ence an “OVERCRANK” fault. This is due to accumu-
lated air in the fuel system during installation. Reset the
control board by pressing the OFF mode button and
ENTER button, and restart up to two more times if neces-
sary. If unit fails to start, contact an Independent Autho-
rized Service Dealer (IASD) for assistance.