Install Manual
Table Of Contents
- Table of Contents
 - Section 1: Safety
 - Section 2: General Information
 - Section 3: Installation
- Introduction to Installation
 - Inverter Versions Compatibility
 - Mounting
 - Open Enclosure
 - Connecting Utility and Standby Power Sources
 - Connecting the ATS Control Cable
 - Connecting the Current Transformer (CTs)
 - Connecting PWRcell ATS Controller
 - Connecting the Grid Sense Wires
 - Manual Override Button
 - Configuring the Inverter
 - Fault Current Label
 
 - Section 4: Operation
 - Section 5: Drawings and Diagrams
 
Installation
10 Automatic Transfer Switch Owner’s Manual
Figure 3-1. Open Enclosure
Connecting Utility and Standby Power 
Sources
Installation and interconnection diagrams are provided in
this manual. 
NOTE: All installations must comply with national, state
and local codes. It is the responsibility of the installer to
perform  an  installation  that  will  pass  the  final  electrical
inspection.
1. Remove  the  finger  safe  barrier  covers  and  then
connect  utility  supply  at  the  utility  service
disconnect  circuit  breaker  terminals  N1  and  N2.
Follow  torque  specifications  listed  on  the  circuit
breaker.
2. See  Figure  3-2.  Connect  utility  neutral  conductor
to  the  neutral  terminal  bar.  The  grounding
electrode  conductors  can  be  connected  to  the
equipment  grounding  terminal  bar  (see  NEC
250.24(A)(4)).  Follow  all  torque  specifications  for
the terminal bars. A wire type main bonding jumper
is provided to properly bond the service equipment.
NOTE:  A  wire  type  main  bonding  jumper  (A)  is
provided  on  200  A  units  and  100  A  Service
Entrance rated units. This bonding jumper  can be
removed if needed where the ATS is not  installed
as service equipment.
NOTE:  Service  entrance  rated  model will  have  a
service disconnect in area (B) of Figure 3-3.
3. Connect  the  inverter  protected  load  ungrounded
feeder  conductors  to  terminals  E1  and  E2  on  the
transfer mechanism.
4. Connect  the  inverter  protected  load  neutral
conductor to the neutral terminal bar. Connect the
inverter  protected  load  equipment  grounding
conductor to the equipment grounding terminal bar.
Follow  all  torque  specifications  for  the  terminal
bars. 
5. Connect  a  subpanel  supply  to  lower  T1  and  T2
Terminals. Connect subpanel Neutral conductor to
the  neutral  terminal  bar  and  the  equipment
grounding  conductor  to  the  equipment  ground
Copper  or Aluminum  conductors shall  be  sized  in
accordance with all applicable NEC requirements,
and  shall  be  permitted  to  be  sized  based  on  the
75°C  column  of  Table  310.16  in  the  NEC.  The
installation  must  comply  fully  with  all  applicable
codes, standards and regulations.
Knockouts  into  the  transfer  switch  can  be  made  in  the
field  as  needed  for  entry  of  power  cables  and  conduit.
Conduit  entry  shall  maintain  the  proper  wire  bending
spaces required by Tables 312.6 (A) and (B) in the NEC.
For  transfer  switches  installed  in  wet  locations,  power
004397
D
E
B
A
C
J
H
F
G
(000116)
DANGER
Electrocution. Turn utility and emergency 
power supplies to OFF before connecting 
power source and load lines. Failure to do so 
will result in death or serious injury.










