Product Manual
Installation
8 Homelink Upgradeable Manual Transfer Switch Owner’s Manual
Automatic Upgrade Kit
Installation
1. Turn transfer switch normal power supply circuit
breaker OFF (open).
2. Remove transfer switch cover, disconnect control
wiring to cover, and verify electrical power has
been turned off.
3. Disconnect normal power feeder conductors, the
generator feeder conductors, and panelboard
conductors from transfer mechanism.
4. See Figure 3-3. Remove screw (A) that holds the
transfer mechanism in place, and remove transfer
mechanism from the transfer switch.
Figure 3-3. Remove Transfer Mechanism
5.
See
Figure 3-4
. Remove lower left screw (B)
securing divider plate in the transfer switch.
Figure 3-4. Install Automatic Back Plate
6. Install new automatic back plate (C) in transfer
switch and secure to transfer switch enclosure.
7. Remove neutral conductor from main lug on
neutral bar.
8. See Figure 9. Terminate normal power neutral to
main lug (D) on neutral bar.
Figure 3-5. Connection Details
9. Terminate neutral conductor from generator power
feeder on neutral terminal bar (E) in transfer
switch.
10.
Terminate normal power feeder conductors to N1 and
N2 (F) on transfer mechanism.
11.
Terminate panelboard feeder conductors to T1 and T2
(G) on transfer mechanism.
12.
Terminate generator feeder conductors to E1 and E2
(H) on transfer mechanism.
13. Terminate generator control wiring to N1, N2, T1,
23 and 194 terminals (J) in transfer switch.
14. Install new panelboard cover and properly label all
branch circuits.
15. See Section 4 Checking Automatic Operation
(Automatic HSB Generator Only) to verify proper
transfer switch and generator operation.
A
B
C
G
H
F
D
E
J