Product Manual
Activation and Startup
18 Owner’s Manual for Stationary Generators
position.  The  switch  is  now  powered  by  the 
standby generator.
8. T
urn  ON  the  circuit  breaker/electrical  loads 
powered by the generator.
9. Con
nect a calibrated AC voltmeter and a frequency 
meter across terminal lugs E1, E2, and E3 (if three 
phase). Voltage should be approximately unit rated 
voltage. Check with clamp on amp meter to ensure 
unit is not overloaded.
10. L
et  the  generator  run  at  full  rated  load  for  20-30 
minutes.  Listen  for  unusual  noises,  vibration,  or 
other indications of abnormal operation. Check for 
oil leaks, evidence of overheating, etc.
11. Whe
n  testing  under  load  is  complete,  turn  OFF 
electrical loads.
12. Move 
the  Main  Circuit  Breaker  switch  on  the 
generator  control  panel  up  to  the  OFF  (or  open) 
position. 
13. Allo
w the engine to run at no-load for 2-5 minutes.
14. Pr
ess OFF on the control panel to shut the engine 
down.  A  red  LED  illuminates  to  confirm  that  the 
system is in the OFF mode.
Test Auxiliary Shutdown Switch Operation
The generator is equipped with an independent means of 
shutting  down  prime  mover  (engine)  for  use  in  emer-
gency  situations. The shutdown  mechanism,  when  acti-
vated, requires a mechanical reset. 
See  Figure 3-6.  Generators  15  kW  and  larger  are 
equipped 
with two auxiliary shutdown switches. One aux-
iliary shutdown switch (A) is located 
on the generator roof 
above and to the right of the viewing window. The second 
auxiliary shutdown switch (B) is inside the control panel 
enclosure.
004900
ON
OFF
ENGINE
SHUTDOWN
004890
A
B
Figure 3-6. Auxiliary Shutdown Switches
Test auxiliary shutdown switches 
after installation to ver-
ify correct operation.
1. V
erify auxiliary shutdown switches are ON (I).
2. Pre
ss  MANUAL  key  on  control  panel  keypad  to 
start engine.
3. With 
engine  running,  set  one  auxiliary  shutdown 
switch to OFF (O). Engine should shut down imme-
diately.
• If 
engine  stops,  set  auxiliary  shutdown  switch  to 
ON (I), clear alarm on controller, and restart engine 
to verify generator is operating normally. After veri-
fying normal operation of first 
auxiliary switch, ver-
ify operation of second auxiliary s
witch.
• If 
engine  does  not  stop,  auxiliary  shutdown 
switch  is  not  functioning  correctly.  Contact  an 
IASD.
NOTE: Aux
iliary shutdown switches are not intended to 
be a  primary means to shut  down generator under nor-
mal operating conditions. Accide
ntal activation of an aux-
iliary  shutdown  switch  will  prevent 
generator  from 
operating during a power outage.
Check Automatic Operation
To  check  the  system  for  proper  automatic  operation, 
proceed as follows:
1. V
erify that the generator is OFF. A red LED on the 
control panel illuminates to confirm that the system 
is in the OFF mode.
2. Inst
all front cover of the transfer switch.
3. T
urn  ON  the  utility  power  supply  to  the  transfer 
switch, using the means provided (such as a utility 
main line circuit breaker).
NOTE:  T
ransfer  Switch  will  transfer  back  to  utility 
position.
4. Mo
ve  the  Main  Circuit  Breaker  switch  on  the 
generator  control  panel  up  to  the  ON  (or  closed) 
position. 
5. Pre
ss AUTO  on  the  control  panel.  The  system  is 
now ready for automatic operation.
6. T
urn  OFF  the  utility  power  supply  to  the  transfer 
switch.
With  the  generator  ready  for  automatic  operation,  the 
engine 
will crank and start when the utility source power 
is  turned  OFF  after  a  10  second  delay  (factory  default 
setting). After starting, the transfer switch connects load 
circuits  to  the  standby  side.  Let  the  system  operate 
through its entire automatic sequence of operation.
With  the  generator  running  and  loads  powered  by 
generator 
AC output, turn ON the utility power supply to 
the  transfer  switch.  The  system  transfers  back  to  the 
utility position and then runs through the cool down cycle 
and shuts down.










