Control Panel Startup / Testing
Installation Guidelines for 60 Hz Air-Cooled Generators 41
4. Generator will start and run. Allow generator to run
and warm up for a few minutes.
5. Set generator MLCB (generator disconnect) to ON
(CLOSED).
6. Set utility MLCB to ON (CLOSED).
The system now operates in automatic mode. 