8 Installation Guidelines for 60 Hz Air-Cooled Generators
IMPORTANT NOTE: DO NOT perform next step until 
generator has been transported to installation site.
4. See Figure 2-3. Remove bolts and pallet brackets
(A).  Exercise  caution  when  removing  generator.
Dragging  it  off  pallet  will  damage  base.  The  unit
must be lifted from wooden pallet to remove.
NOTE:  Bolts  and  pallet  brackets  are  provided  only  for
shipping purposes and can be discarded after removal. 
Figure 2-3. Pallet Bracket Locations
Opening the Lid
1. Use keys to open generator lid.
2. See Figure 2-4. Two locks (A) secure lid; one on
each side. Press down on lid above side lock, and
unlock latch to correctly open lid.
Figure 2-4. Opening the Lid
3. Repeat for other side. Lid may appear stuck if pres-
sure is not applied from the top.
NOTE:  Always  verify  side  locks  are  unlocked  before
attempting to lift lid.
Enclosure Panel Removal
Generator installation requires removal of front panel and
intake  side  panel.  Remove  these  panels  when  neces-
sary. Proceed as follows to remove the panels.
Remove Front Access Panel
See Figure 2-5. Remove front access panel (A) by lifting
straight up and out once lid is open.
NOTE: Always lift front access panel straight up before
pulling away from enclosure (B and C). Do not pull panel
away from the enclosure before lifting up (D).
Figure 2-5. Remove Front Access Panel