Install Manual
Table Of Contents
- Installation Guidelines
- FREQUENTLY ASKED QUESTIONS
 - Table of Contents
 - Section 1 Safety and General Information
 - Section 2 Unpacking and Inspection
 - Section 3 Site Selection and Preparation
 - Section 4 Generator Placement
 - Section 5 Fuel Conversion/Gas Connections
 - Section 6 Electrical Connections
 - Section 7 Control Panel
 - Section 8 Troubleshooting
 - Section 9 Quick Reference Guide
 - Section 10 Accessories
 - Section 11 Diagrams
 - Part No. 0K5804
 
 
Control Panel
Installation Guidelines for Air-Cooled Generators 39
13. Set the generator’s main circuit breaker to the OFF (or open) position.
14. Let the engine run at no-load for 2-5 minutes.
15. Push the generator’s OFF button. The engine should shut down.
7.7 — Checking Automatic Operation
To check the system for proper automatic operation, proceed as follows:
1. Ensure that the generator is OFF.
2. Install front cover of the transfer switch.
3. Turn ON the utility power supply to the transfer switch, using the means provided (such as a utility main line cir-
cuit breaker).
NOTE: Transfer Switch will transfer back to utility position.
4. Set the generator’s main circuit breaker to its ON (or CLOSED) position.
5. Push the generator’s AUTO button. The system is now ready for automatic operation.
6. Turn OFF the utility power supply to the transfer switch.
With the generator ready for automatic operation, the engine should crank and start when the utility source power is 
turned OFF after a 5 second delay (factory default setting). After starting, the transfer switch should connect load cir-
cuits to the standby side after a five (5) second delay. Let the system operate through its entire automatic sequence of 
operation.
With the generator running and loads powered by generator AC output, turn ON the utility power supply to the transfer 
switch. The following should occur:
• After approximately 10 seconds, the switch should transfer loads back to the utility power source.
• Approximately one minute after re-transfer, the engine should shut down.
7.8 — Installation Summary
1. Ensure that the installation has been properly performed as outlined by the manufacturer and that it meets all 
applicable laws and codes.
2. Test and confirm proper operation of the system as outlined in the appropriate installation and owner’s manuals.
3. Educate the end-user on the proper operation, maintenance and service call procedures.
IMPORTANT! If the end user ever finds it necessary to turn the generator off during prolonged utility outages 
to perform maintenance or conserve fuel, educate them on these simple, but important steps:
To turn the generator OFF (while running in AUTO and online):
1. Turn OFF (or OPEN) the main Utility disconnect.
2. Turn OFF (or OPEN) the Main Line Circuit Breaker (MLCB) on the generator.
3. Turn the generator OFF. If the generator will remain off for more than an hour, remove the 7.5 Amp fuse from the 
control panel to avoid draining the strating battery, if utility is not present.
To turn the generator back ON:
1. Put the generator back into AUTO and allow to start and warm-up for a few minutes.
2. Turn ON (or CLOSE) the MLCB on the generator.
The system will now be operating in its automatic mode. The main utility disconnect can be turned ON (or CLOSED), 
but to shut the unit off, this complete process must be repeated.