Owner manual

12
D
GB
F
E
09702-09.2013-DGbF
5| Compressor assembly
5.1 Setting up
Set up on an even surface or frame with sufcient load-bearing
capacity.
Compressors and drive motors are basically rigid and should be
mounted together on a base frame.
Provide adequate clearance for maintenance work.
Provide adequate ventilation for the drive motor.
Do not use in a dusty, damp atmosphere or a combustible
environment.
INFO! New compressors are factory-lled with inert gas (3 bar nitrogen).
Leave this service charge in the compressor for as long as possible
and prevent the ingress of air.
Check the compressor for transport damage before starting any
work.
Fig. 13
Fig. 14
Fig. 15
Fig. 11
Transport and suspension unit on the eyebolt (Fig. 12, F14 to F16) or direct on the discharge
line valve (Fig. 11, F2 to F5).
WARNING! Move compressors only with hoists that have adequate load-bearing
capacity.
Fittings (e.g. pipe holders, additional units etc.) on the compressor are permissible only
following consultation with Bock.
Setup on an even surface or frame with sufcient load-bearing capacity. Use all 4 fastening
points.
Correct setup of the compressor and mounting of the belt drive are decisive for running comfort,
operating safety and the service life of the compressor.
Fig. 12