Changing the Historical View Start and End Dates
The Historical View start and end date field is set up as mm/dd/yyyy. There are two methods
for changing the PST Start and End Date fields. You can:
Click on each parameter of the date field; i.e. mm, or dd, or yyyy, and change each
individual parameter.
or
Access the calendar in the drop down of the date field.
To change the start date schedule for the next PST:
1. Either:
a. Click in each parameter (mm-dd-yy-hh-mm) of the date field and highlight the text.
b. Type over the old value with the new value for each parameter
or
a. Click in the drop down, located at the right of PST schedule date field and access the
date calendar (Figure 301).
b. Using the arrow key on the calendar, change the month, if necessary.
c. When in the correct month on the calendar, drag the mouse and click on the correct
date within the month.